Using P6 and EVM to calculate profit/loss

صفحة 2 من 2 الأولىالأولى 1 2
النتائج 11 إلى 14 من 14
  1. [11]
    qazi
    qazi غير متواجد حالياً
    جديد


    تاريخ التسجيل: Jan 2007
    المشاركات: 8
    Thumbs Up
    Received: 0
    Given: 0
    Dear
    according to the plan, its required from the contractor to submit soft copy or hard copy for the plan , as PDF not premavera file, then in your first question you are comparing EV with BCWS so you dont compare with the selling price what ever the selling price , (for that its called cost control not price control-even its easy to monitor the Actual cost with selling price-) , EV its internal procedure in the contracting company ,

    0 Not allowed!



  2. [12]
    Eng.Amin
    Eng.Amin غير متواجد حالياً
    جديد


    تاريخ التسجيل: Feb 2009
    المشاركات: 1
    Thumbs Up
    Received: 0
    Given: 0
    معذرة الرد سيكون باللغة العربية
    وأرجو الرد اذا كانت اجابتى خاطئة
    أعتقد أنه عمل تحميل للتكاليف الفعلية يكون للبنود التى تم تنفيذها عمليا على حسب نسب التنفيذ الموجودة على ارض الواقع والتى تم وضعها بالمستخلص بالأحرى حيث يتم تحميل مراكز التكلفة بالتكاليف الفعلية وليس بما تم صرفه اليوم
    حيث سيكون وقتها التقاريرساعتها اكثر واقعية ويمكن ساعتها ارفاق تقرير من الحسابات بما تم صرفه حتى الأن على كل مركز تكلفة خاصة بالنسبة لمقاولى الباطن والتى تخرج بصورة مدين ودائن
    وبذلك يكون تقرير التخطيط عبارة عن التكلفة الفعلية التى تم تنفيذها بالموقع
    وتقرير الحسابات بالتكاليف التى تم انفاقها فعليا حتى اليوم
    ويكون الفرق بينهما هى مستحقات المقاولين عن الفترة الماضية من العمل والتى لم تصرف لهم حتى حينه

    أما بالنسبة لفترات التأمين والتدفقات المالية فيمكن اظهارها بصورتها الطبيعية
    وهى ما تم صرفه لى من مستخلصات حتى حينه

    0 Not allowed!



  3. [13]
    المفكرةالعربيه
    المفكرةالعربيه غير متواجد حالياً
    تم إيقافه لمخالفة القوانين
    الصورة الرمزية المفكرةالعربيه


    تاريخ التسجيل: Apr 2008
    المشاركات: 410
    Thumbs Up
    Received: 1
    Given: 0
    Qazi,

    Internally AND in lump sum, you woiuldn't care about the budget submitted to owner ( selling budget), becasue the earned value will be yours, however, if you go back and read my previous comment to be careful about type of contract, in cost plus, you still have to submit the Earned value system to owner, do you give him your actual cost?? or your actual estimate at completion and show the profit?, that is why with owner we have to work with the marked up budget ( for
    simplicity, I called it selling budget

    Regards

    Regards


    اقتباس المشاركة الأصلية كتبت بواسطة qazi مشاهدة المشاركة
    Dear
    according to the plan, its required from the contractor to submit soft copy or hard copy for the plan , as PDF not premavera file, then in your first question you are comparing EV with BCWS so you dont compare with the selling price what ever the selling price , (for that its called cost control not price control-even its easy to monitor the Actual cost with selling price-) , EV its internal procedure in the contracting company ,

    0 Not allowed!



  4. [14]
    qazi12
    qazi12 غير متواجد حالياً
    عضو


    تاريخ التسجيل: Jun 2007
    المشاركات: 10
    Thumbs Up
    Received: 0
    Given: 0
    what i meant in my reply was not for cost plus contract i meant unit price so, sorry for misynderstanding

    0 Not allowed!



  