رPercentage of activities that are critical or near-critical: Many specifications limit the percentage of activities that can be critical or near-critical in the Baseline Schedule. A typical upper limit is a maximum of 30% critical and 50% critical or near-critical. Near-critical may be any float equal or less than 10