    سؤال فى ال time claim

    السلام عليكم
    لدى سؤال فى ال time cliam

    Activity 1-IFC, Planned Received IFC(Excavation): 1-July-2007, duration of the Activity A (Excavation) :50days ,planned start date: 15-
    July-2007

    Activity B, IFC of Foundation
    Planned received date: 20-July-07

    Activity C, Concrete Foundation
    Duration of concrete:70days, Planned Started F.S with the Excavation

    but the IFC Rev were
    Rev.1 Excavation dated 1-July-08+
    Rev.2 Excavation dated 13-July-08
    Rev.3 Excavation dated 20-August -08
    Rev.4 Excavation dated 28-August-08

    Rev. 1 Concrete foundation dated : 25-July-08
    Rev. 2 Excavation Dated :28-August -08

    with this information
    at 20 August:
    Progress% Excavation dated : 30%
    Concrete: 15% for example

    at 28-August
    Excavation :90%

    Thank you very much
    I would like to know the method and procedure for extension time claim and i will consider the update or not

    Concrete:90%

    من مواضيع مخطط مشروعات :


    0 Not allowed!



  2. [2]
    الجنزوري محمد
    الجنزوري محمد غير متواجد حالياً
    عضو متميز


    تاريخ التسجيل: Nov 2006
    المشاركات: 290
    Thumbs Up
    Received: 5
    Given: 1
    Good Question i am waiting the answer

    0 Not allowed!



  3. [3]
    Mouneer,PMP
    Mouneer,PMP غير متواجد حالياً
    عضو فعال
    الصورة الرمزية Mouneer,PMP


    تاريخ التسجيل: Dec 2005
    المشاركات: 57
    Thumbs Up
    Received: 4
    Given: 0
    what do u mean by:
    but the IFC Rev were
    Rev.1 Excavation dated 1-July-08+
    Rev.2 Excavation dated 13-July-08
    Rev.3 Excavation dated 20-August -08
    Rev.4 Excavation dated 28-August-08

    0 Not allowed!



  4. [4]
    مخطط مشروعات
    مخطط مشروعات غير متواجد حالياً
    جديد


    تاريخ التسجيل: Jul 2008
    المشاركات: 3
    Thumbs Up
    Received: 0
    Given: 0
    اقتباس المشاركة الأصلية كتبت بواسطة Mouneer,PMP مشاهدة المشاركة
    what do u mean by:
    but the IFC Rev were
    Rev.1 Excavation dated 1-July-08+
    Rev.2 Excavation dated 13-July-08
    Rev.3 Excavation dated 20-August -08
    Rev.4 Excavation dated 28-August-08
    IFC means
    Issue for contruction
    and it were a lot of rev.
    قام المالك باصدار IFC مرات كثيرة
    الحفر و الخرسانات
    و التواريخ كما هو مبين سابقا
    و شكرا

    0 Not allowed!



  5. [5]
    E.Mohamed Hendy
    E.Mohamed Hendy غير متواجد حالياً
    عضو متميز
    الصورة الرمزية E.Mohamed Hendy


    تاريخ التسجيل: Jul 2007
    المشاركات: 257
    Thumbs Up
    Received: 1
    Given: 0
    ........................

    0 Not allowed!



  6. [6]
    mohamedsaid78
    mohamedsaid78 غير متواجد حالياً
    عضو فعال


    تاريخ التسجيل: Jun 2007
    المشاركات: 71
    Thumbs Up
    Received: 0
    Given: 0
    u must refer to your contract conditions about how to calculate the extension of time is it will according to the updated status of the project or according to the Baseline Schedule.
    Secondly you must know that in 95 % of the E.O.T u gonna claim only for the negative float u had due to this impact u can't claim for all the delayed period cuz the consaltant in the most of the situtations will not approved an E.O.T for an activity still having +total float after retriving the impact event

    0 Not allowed!



  7. [7]
    virtualknight
    virtualknight غير متواجد حالياً
    عضو متميز


    تاريخ التسجيل: Sep 2006
    المشاركات: 857
    Thumbs Up
    Received: 3
    Given: 0
    شكرا جزيلا

    0 Not allowed!



  8. [8]
    Jamal
    Jamal غير متواجد حالياً
    عضو متميز جداً
    الصورة الرمزية Jamal


    تاريخ التسجيل: Apr 2006
    المشاركات: 1,499
    Thumbs Up
    Received: 12
    Given: 5
    Thanx all

    0 Not allowed!



  9. [9]
    mos
    mos غير متواجد حالياً
    عضو متميز


    تاريخ التسجيل: Nov 2005
    المشاركات: 581
    Thumbs Up
    Received: 21
    Given: 1
    أخى الكريم
    تمديد وقت المشروع مرتبط بنوعية ومنطوق بنود العقد
    وعموما المقاول يستحق التعويض زمنيا و أو ماديا عن التأخير بسبب المالك ere
    وللتأخير المعطل فقط للمسار الحرج وليس للمقاول الحق التعويض عن فترات العوم التى هى من حق المشروع.

    مع خالص الشكر

    0 Not allowed!



  10. [10]
    lostlove515
    lostlove515 غير متواجد حالياً
    عضو فعال


    تاريخ التسجيل: Jun 2005
    المشاركات: 88
    Thumbs Up
    Received: 6
    Given: 1
    جزاك الله خيرا

    0 Not allowed!



  
صفحة 1 من 2 12 الأخيرةالأخيرة
الكلمات الدلالية لهذا الموضوع

عرض سحابة الكلمة الدلالية

RSS RSS 2.0 XML MAP HTML